2022

Major design upgrade - residential unit count increased from 159 to 225

In 2022, the Rubio Village Project achieved a significant milestone in its planning and design development: the residential unit count was successfully increased from 159 to 225 units through a comprehensive design optimization process.

This major enhancement was accomplished while preserving the project’s architectural character, urban design intent, and overall site circulation. The revised scheme not only increases land-use efficiency, but also strengthens community programming and long-term project value.

The optimization provides a more efficient layout for residential living, improves amenity distribution, and creates a stronger foundation for the subsequent phases of construction documentation, agency coordination, and permitting.

December 2025

Grading, excavation & shoring permit successfully issued

In December 2025, the Rubio Village Project successfully obtained its Grading, Excavation & Shoring Permit, marking a major milestone in the project’s transition from pre-construction to active construction.

With the permit now issued, the construction team will proceed with site excavation, earthwork operations, and foundation preparation, initiating the first phase of on-site construction activities.

Panku Inc. continues to work closely with all relevant city departments to maintain a smooth approval process and ensure timely progress as the project advances into full construction.

2025–2028

Construction outlook and key milestones

The Rubio Village Project is scheduled to begin on-site construction in January 2026, progressing through the following major phases:

• 2026–2027: Concrete Structure Phase: Construction of the two levels of underground parking and the main superstructure.

• Q1 2027: Framing Phase: The architectural form of the buildings will begin to take shape.

• Q2–Q3 2027: Roofing & Enclosure Phase: Roof waterproofing, insulation, exterior walls, and façade installation.

• July 2027: Roof Dry-In Milestone: The structure will achieve full weather protection, allowing interior work to proceed efficiently.

• Target Completion: Q2 2028: Substantial completion is planned for the second quarter of 2028.